Al Tariq Al Eali Cont Oman, has been awarded Scaffolding Works in Marjan Increment Programme Package-II at Larsen and Toubro Modular Fabrication Yard, Sohar. Executed a Cubic Mtr 5173 during Jun 2022 to March 2025.
CRPO 78 – Cubic Mtr 97772 Duration 1st Aug 2023 to 29 Feb 2024
CRPO 88 89 90 : – Cubic Mtr 169600 Duration 1st Aug 2023 to 31st March 2024
CRPO 97 Cubic Mtr 41681 Duration 1st Jan 2024 to 30 April 2024
CRPO 98 Cubic Mtr 9617 Duration 1st May 2024 to 30 June 2024
CRPO 80 81 Cubic Mtr 3,76,478 Duration : 1st Aug 2023 to 30 Sep 2025
MOGAS Cubic Mtr 22,500 Duration : 31st July 2025 31 Aug 2025
CRPO 117 118 119 Cubic Mtr 571504 Duration : 1st May 2024 to still going on
For above
Owner: Saudi Aramco
Client: Larsen and Toubro